Monday, September 13, 2010

1st operation with the PV system for one hour!

On Saturday after the long "running" procedure powered by grid, we connected the system with the PVs! It was around 17:00 and it worked perfect, with no a lot of fluctuations until 18:00. 

desalination with PV!
no grid, only sun!
First water from the sun!



Feed flow = 5gpm
Permeate flow = 1 gpm
Membrane pressure= 55 bar
ΔP at prefilter = 1 bar
Permeate conductivity = 1200 μS/cm corresponding to 780.96 mg/l.


The permeate quality is an issue we have to deal with today.



At 18:00 the irradiation fell abruptly because of heavy clouds, and then we had to stop the system. 

Today we are starting operation with PVs and see how it will go!

No comments: